In 2015, the Thames Tideway Tunnel cleared at roughly 4% real Cost of Equity (CoE); this month, fresh capital for Sizewell C was priced at 10.8%. The doubling of required returns in UK infrastructure is a market reality, not a regulatory choice—and it places Ofwat in a delicate position. Tasked with maintaining consumer affordability even as the water sector needs roughly £60 billion of new capital in the next five years[i], the regulator must translate policy ambition into an allowed return that can attract capital.
That challenge crystallises in the Beckton Water Recycling Plant, one of the first big tests of Ofwat’s Direct Procurement for Customers (DPC) scheme and a bellwether for the £40 billion pipeline[ii] that follows. A DPC is a competitive auction in which a water company tenders a large, discrete project to a third-party provider, with the aim of securing lower lifetime costs for customers than building in-house. Vallorii’s analysis puts Beckton’s real CoE at 9.2–9.6%, about four points above the 5.1% allowed in PR24. That higher required return translates into larger annual payments demanded by the provider—costs that ultimately flow into household bills.
Vallorii estimates 9.2-9.6% for Beckton Water Recycling, more than 400 bps above regulatory norms
Cost of Equity (% real)
Market Conditions
Ofwat CAPM at 70% gearing6.3
- Current market conditions
6.6–8.2
Asset-specific risks
Construction risks9.5–10.6
- Counterparty risks
11.0–12.4
- Asset health risks
11.0–12.4
Risk allocation
Contractor underwriting9.6–10.3
- Consumer underwriting
9.2–9.6
Show the data as a table
| % | |
|---|---|
| Ofwat CAPM at 70% gearing | 6.3 |
| Current market conditions | 6.6–8.2 |
| Construction risks | 9.5–10.6 |
| Counterparty risks | 11.0–12.4 |
| Asset health risks | 11.0–12.4 |
| Contractor underwriting | 9.6–10.3 |
| Consumer underwriting | 9.2–9.6 |
The premium is rooted in evidence. Vallorii’s asset-pricing engine generated about a million scenarios, then tied each to hard data. The model found 3 key insights.
- A study of 1,093 UK water-infrastructure construction projects shows fat tailed cost overrun risk[iii]; feeding that distribution into Beckton’s capital expenditure budget adds 240–290 basis points to the Cost of Equity.
- Counterparty risk contributes another 150–190 bps: Thames Water’s CCC junk-grade credit rating implies substantial risk of payment default. DPC projects rely solely on the Appointee water company to deliver annual payments, and the risk of a Thames Water bankruptcy heightens cash flow uncertainty.
- By contrast, asset-health is not a significant risk. Performance penalties are capped at about a tenth of annual revenue[iv] and the project’s terminal value will be heavily depreciated, so even extreme asset-condition shocks barely register against construction or counterparty volatility. As a result, asset-health contributes near-zero incremental CoE for a new-build plant (though it can dominate brownfield appraisals once construction risk subsides).
Vallorii’s modelling shows that allocating these risks explicitly can soften investors’ demands. One option is a fixed-price construction contract: the construction contractor, not the investor, eats any cost overruns, trimming the required return by more than a percentage point. The snag is that most contractors run on razor thin margins; a major overspend can push them into insolvency, throwing the bill back onto investors. A sturdier—though politically sensitive—remedy is for consumers or government to underwrite the worst outcomes, from extreme overruns to a Thames Water default. Vallorii’s modelling can stack these safeguards one by one, quantifying how each cushion nudges Beckton’s CoE closer to levels acceptable to both investors and bill-payers.
Going a step further—ring-fencing the scheme as a Thames Tideway-style standalone provider (a ‘SIPR’)—could push the CoE lower still, a route we will unpack in an upcoming post. In an era of dear capital, such calibrated cushions offer Ofwat the best shot at pairing policy ambition with affordable bills.
In an era of dear capital, such calibrated cushions offer Ofwat the best shot at pairing policy ambition with affordable bills.
Sources
- [i]Ofwat APRs & PR24 FD
- [ii]Ofwat: A Major Projects guide for investors
- [iii]https://www.pure.ed.ac.uk/ws/portalfiles/portal/58554009/Cost_Profiling_of_Water_Infrastructure_Projects_2018_JIS_Author_s_Copy.pdf (opens in a new tab)
- [iv]Ofwat’s DPC contracts replicate the SPV model’s core features—competitively appointed vehicle, ~25-year availability-based revenue outside the RAB—regulators are likely to transplant the SPV precedent Macquarie cites (opens in a new tab), namely a 10 % cap on annual revenue deductions for performance shortfalls, to keep financing costs competitive
More research

Vallorii AI Forecasts 28–93% Drop in UK Gas Demand by 2050, Against a 7–56% Reduction in Gas Grid Use
Utility companies and infrastructure investors face a central challenge in the UK’s energy transition: how to plan under deep...

Lennart Baumgärtner
3 min read

Thematic Report: Time for a Change? Cost of Capital for future-proof Infrastructure
CAPM, CAPM+ or bottom-up? Our new paper explores what’s next for the cost of capital in UK infrastructure.

Robert Ritz
1 min read